Melbourne Metro Rail Project

CBD North Station Design & Documentation Management

My Role

Design Team Member & Project-wide Document Controller.

As a design team member for the CBD North Station my role was to coordinate and produce technical design information to guide construction.

As the Project-wide Document Controller for the full consortium, I implemented structured document management workflows, enabling large-scale coordination between architects, engineers, project managers, and client representatives.

Project Objectives

The Melbourne Metro Rail Project is a $13B infrastructure initiative to deliver five new underground stations and associated rail tunnels across Melbourne. Each of the five underground stations required a cross-disciplinary team and stakeholders that operated within a wider consortium. With multiple disciplines and stakeholders producing vast volumes of technical design content (often exceeding 500+ drawings per milestone for each of the five stations), the project needed a robust process to manage, track, and deliver design documentation. Timelines were tight, project milestones were critical, and accuracy was non-negotiable.

Key Features

Centralised Document Control System – Ensured accessibility, accuracy, and compliance for all design files.

Cross-Disciplinary Coordination – Structured document management workflows, enabling large-scale coordination between architects, engineers, project managers, and client representatives.

Version Control & Compliance – Maintained high data integrity and adherence to contractual procedures.

Milestone Delivery Tracking – Monitored progress to meet deadlines and handover requirements.

Stakeholders

Rail Projects Victoria, Metro Trains Melbourne, John Holland, CPB Contractors, AECOM, Public Transport Victoria, V/Line, VicTrack, The City of Melbourne

Key Outcomes

Delivered design documentation for CBD North Station to construction readiness.

Successfully managed document control across all five stations, coordinating 500+ drawings per milestone.

Established robust processes for accuracy, compliance, and workflow management in one of Australia’s largest infrastructure projects.

What I learnt

Leadership & Cross-discipline collaboration | Stakeholder Management & Communication | Complex Project Planning & Delivery | Systems thinking and integration | User-centered design & human impact | Decision making under constraints | Governance & risk management

Cross-discipline Collaboration

3D coordination of combined design, engineering and construction input for CBD North Station.